Uncategorized

BENECO Power Interruption Schedule for July 20-25, 2020 Affecting Baguio City and Benguet





The Benguet Electric Cooperative, Inc., (BENECO) has released the schedule of Electric Service Interruption for July 20 – July 25, 2020, affecting several areas in Baguio City and Benguet.

BENECO Power Interruption Schedule from July 20 – July 25, 2020

Here are the following areas in Baguio City and Benguet affected by the scheduled power interruption scheduled on July 20 – July 25, 2020.

Date Areas Affected Purpose

July 20,2020

(9:00 am – 5:00 pm)

Baguio City: Parts of Engineer’s Hill Uprating of 2/0 conductor wire with 4/0 conductor wire
Baguio City: Parts of South Central Aurora Hill Relocation of 1 unit 30’ steel pole
La Trinidad: Parts of Km. 4 Uprating of Communal DT from 75Kva TO 100kVA
La Trinidad: Parts of Lower Wangal

Sablan: Oring, Banengbeng

  • Installation of Lighting Arrester
  • Massive Line Clearing

July 21, 2020

(9:00 am – 5:00 pm)

Baguio City: Purok 5, Pinsao Proper Correction of Secondary Line Clearance
La Trinidad: Parts of Bahong La Trinidad Uprating of 2/0 conductor wire with 4/0 conductor wire
Baguio City: Purok 1, Pinsao Pilot Project Rerouting of Secondary Lines

July 22, 2020

(9:00 am – 5:00 pm)

Baguio City: Parts of Happy Homes-Lucban and Camdas Relocation of Poles
Baguio City: Parts of Bacbacan, Km. 4, and Pacday Quino, Asin Road Barangay Correction of Secondary Line Clearance
Tuba: Parts of Taloy Norte Uprating of 5Kva Distribution transformer to 10kVa transformer

July 23, 2020

(9:00 am – 5:00 pm)

Parts of Botiwtiw Ambiong, Baguio, Teacher’s Village, SLUSVP Replacement of 40’ Creosoted Pole with 40’ concrete Pole
Parts of Beckel, La Trinidad Relocation of 1 unit 35’concrete pole
Parts of Tuding, Itogon Rerouting of Secondary Lines

July 24, 2020

(9:00 am – 5:00 pm)

Parts of Purok 5, Pinsao Pilot Proper Relocation of Pole
Parts of Upper Kayang Extension Relocation of Pole
Parts of Tuding, Itogon Relocation of Pole
Parts of Banangan, Sablan Replacement of Rotten Pole

July 25, 2020

(9:00 am – 5:00 pm)

Whole of Camp 7, Camp 8, Military Cut-off, Parts of BGH Compound, Camp 6, Loakan Proper, Loakan Liwanag, PMA Kias, San Vicente, Balsigan, Camp 5-Camp 1, Dungon, Twin Peaks, Tabaan Sur
  • Relocation of Primary Poles Affected by DOH-BGHMC Projects
  • Reconfiguration of Primary Structure/Secondary Line
  • Relocation of Pole




Cable & Communication Companies

In BENECO’s advisory, all concerned Cable & Communication Companies are advised to inspect and institute necessary safety measures or actions on their cables or lines attached to the affected BENECO poles.

Also, all consumers are advised to always consider all lines energized because power may be restored earlier than the scheduled time.

For other questions and concerns:

For more information and concerns, contact BENECO at any of these numbers:

  • LANDLINE:637-4400 local 605 to 607
  • SMART: 09088657202
  • GLOBE:09175921698

Source: BENECO