BENECO and NGCP Power Interruption from February 8-11, 2022
As announced by the Benguet Electric Cooperative (BENECO), here are areas in Baguio City and Benguet that will be affected by scheduled power interruptions by BENECO and NGCP from Tuesday, February 8, 2022, to Friday, February 11, 2022.
BENECO Power Interruption (February 9 & 11, 2022)
Date and Time | Areas Affected | Purpose |
---|---|---|
February 9, 2022 Wednesday 9:00 AM to 5:00 PM | SABLAN: Abuloy/RRCY (DSWD), Bayabas | Facilitate tree cutting |
BAGUIO CITY: Parts of Purok 6 and Goshenland, Adiwang Rd., Dontogan | Relocation and rerouting of secondary lines to improve line clearance |
|
BAGUIO CITY: Parts of Ongasan, Loakan Proper | Relocation of pole obstructing driveway |
|
BAGUIO CITY: Parts of Pinesville Subdivision Kias, and Fort del Pilar- PMA | Relocation of pole affected by proposed construction |
|
February 11, 2022 Friday 9:00 AM to 5:00 PM | BAGUIO CITY: Parts of Purok 10, Purok 12, Apugan, Irisan | Extension of Primary Lines and Installation of Sole Use Distribution Transformer (DM Foodmart) |
BAGUIO CITY: Upper General Luna (Brent Rd., Yangco Rd., Laubach Rd.) parts of Salud Mitra (along Upper General Luna Rd.) parts Holy Ghost Proper (Sumulong St.) | Installation of Intermediate Pole and Primary Metering Line Clearing |
|
ITOGON: Hartwell, Ampucao | Replacement of rotten pole and reconductoring of secondary lines |
Note: scroll down further for the NGCP power interruption schedule.
NGCP Power Interruption (February 8 & 10, 2022)
Date and Time | Areas Affected | Purpose |
---|---|---|
February 8, 2022 Tuesday 8:00 AM to 12:00 NN and 3:30 PM to 5:00 PM | Whole of Tublay EXCEPT parts of Caponga and Tuel Whole of Kapangan Whole of Kibungan EXCEPT Palina and Tacadang Whole of Atok Whole of Bokod EXCEPT parts of Ambuklao Whole of Kabayan Whole of Bakun EXCEPT Kayapa Parts of Buguias: - Natubleng - Parts of Amgaleyguey (Sinipsip ES, Sinipsip National HS, Sepadan and Pakpakitan, Akiki | To facilitate request of BENECO in relation to their relocation of metering facility project (Mankayan substation) preparatory works |
February 8, 2022 Tuesday 8:00 AM to 5:00 PM | Whole of Buguias EXCEPT Natubleng and parts of Amgaleyguey (Sinipsip ES, Sinipsip Nation HS, Sepadan and Pakpakitan, Akiki Whole of Mankayan Parts of Cervantes, Ilocos Sur | Installation of new 69kV metering instrument transformers at the newly constructed steel pedestal by BENECO at Mankayan substation |
February 10, 2022 Thursday 8:00 AM to 9:30 AM and 3:30 PM to 5:00 PM | Whole of Buguias EXCEPT Natubleng Whole of Mankayan Parts of Cervantes, Ilocos Sur | To facilitate request of BENECO in relation to their relocation of metering facility project (Mankayan substation) preparatory works |
February 10, 2022 Thursday 8:00 AM to 5:00 PM | Whole of Tublay EXCEPT parts of Caponga and Tuel Whole of Kapangan Whole of Kibungan EXCEPT Palina and Tacadang Whole of Atok Whole of Bokod EXCEPT parts of Ambuklao Whole of Kabayan Whole of Bakun EXCEPT Kayapa Parts of Buguias: - Natubleng | Installation of new 69kV metering instrument transformers at the newly constructed steel pedestal by BENECO at Atok Substation Replacement of BENECO 69kV Take-off Woodpole structure at their Atok Substation |
Cable & Communication Companies
In BENECO’s advisory, all concerned Cable & Communication Companies are advised to inspect and institute necessary safety measures or actions on their cables or lines attached to the affected BENECO poles.
For other questions and concerns:
For more information and concerns, contact BENECO at any of these numbers:
- LANDLINE: 637-4400 local 605 to 607
- SMART: 09088657202
- GLOBE: 09175921698
For More News and Updates
Looking for more news and updates? Feel free to explore our BCG website and our official Facebook page. You may also check out our official BCG YouTube channel to catch a variety of video content.
SOURCE: BENECO