As announced by the Benguet Electric Cooperative (BENECO), here are areas in Benguet that will be affected by scheduled power interruptions by BENECO from Monday, February 9, 2026, to Saturday, February 14, 2026.
| Areas Affected | Purpose | |
|---|---|---|
| February 9, 2026 Monday 9:00 AM to 5:00 PM | Whole of Mankayan except Taneg and Guinaoang | Replacement of fuse assemblies Installation of intermediate poles to improve line clearance Installation of smart arresters |
| SABLAN: Parts of Lexber Homes Metro Baguio Subdivision, Banangan | Reconductoring of secondary lines to #4/0 ACSR coated | |
| BAGUIO CITY: Parts of Fairview (Avelino St., including Rainbow Hills Subdivision), parts of Campo Filipino (Roman Ayson Rd., part of Sixto Gaerlan St.) and parts of Ferguson Rd. (from Sudzee Laundry Shop to Petron) | Replacement of sole-use distribution transformers | |
| February 10, 2026 Tuesday 9:00 AM to 5:00 PM | TUBLAY: Sitio Tabeyo Ambassador | Facilitate tree cutting and ROW clearing |
| BOKOD: Sitio Ambayek, Poblacion | Replacement of damaged primary pole | |
| BOKOD: Otbong, Bobok-Bisal | Replacement of wooden secondary pole | |
| ITOGON: Parts of Virac (Keymen's Hill, Kiangan Village, Camp Suerte, Camp 6, Camp 5) | Upgrading of poles and primary extension | |
| BAGUIO CITY: Parts of Pinewoods Subdivision (Engelmann, Juniper, Balsam, Spruce Bend, Cedar Loop, Sierra Bend, Yew Road, Sago, Cypress Bend, part of Conifer Drive), Sta. Lucia | Energization of secondary lines and relocation of service drops | |
| BAGUIO CITY: Parts of San Luis village (Dahlia St., and areas near San Luis Village Barangay Hall) | Relocation of secondary lines affected by ongoing construction | |
| LA TRINIDAD: Parts of Km.5 (Fangonil Street., including Trading post and areas near Provincial Health Office), Pico | Restructuring of primary assemblies for primary extension | |
| BAGUIO CITY: Part of Teachers Camp (areas near Administration office and cottages) | Replacement of damaged secondary pole | |
| February 11, 2026 Wednesday 9:00 AM to 5:00 PM | BAGUIO CITY: Parts of Pinsao Pilot Project (parts of Purok 1, Purok 2, Purok 3, Purok 6, Purok 7, including areas near Pinsao National High School) and part of Riverside, Guisad Central | Reconfiguration of lines for primary extension |
| LA TRINIDAD: Parts of Km 4. (from BIR to Tiongsan) | Replacement and correction of leaning secondary pole | |
| BAGUIO CITY: Parts of Loakan Proper (Pongian, Ongasan, Mangga, Suyoc, Arupong, Demo Mines, Cliff Drive, Maxicar, Sadjo), parts of Camp 7 (areas from Satellite Market until Lion's Head, part of Pias tapped at Satellite, Youngland); TUBA: Parts of Camp 4 (Camp 6, La-aw, Millsite, Hilltop, Riverside, Hydro 1, City Limit) | Relocation of poles affected by DPWH Project Replacement and correction of leaning primary pole | |
| February 12, 2026 Thursday 9:00 AM to 5:00 PM | BOKOD: Sitio Penged and parts of Abiyo, Daclan | Replacement of wooden primary poles Extension of underbuilt secondary lines |
| BAGUIO CITY: Parts of Upper General Luna (Brent Rd., Yangco Rd., Laubach Rd.), parts of Salud Mitra (along Upper Gen. Luna Rd.), and parts of Holy Ghost Proper (Sumulong St. tapped at Yangco Rd.) | Relocation of primary pole affected by ongoing construction | |
| ITOGON: Loacan (Tocmo, Tollibeng, Labilab, Sabkil, Anteg-in, Marooc, Peday, Camisong, Apalan), parts of Tinongdan (Guisset) | Facilitate massive clearing Rerouting of secondary lines affected by ongoing construction | |
| BOKOD: Ambuklao (Banao, Minac, Lebeng, Adonot, Hilltop, Sombrero, Ambangol) | ||
| February 13, 2026 Friday 9:00 AM to 5:00 PM | BAGUIO CITY: Parts of Smith Drive (Visperas Store to Shano Sari-Sari Store), Whole of Purok 6 Dumpsite (Gold Alley, Diamond Alley, Silver Alley, Bronze Alley) | Relocation of secondary lines affected by ongoing construction |
| BAGUIO CITY: Parts of Holyghost Extension (areas from Holy Grace Apartment to Shine Store near Honeymoon Rd.) | Relocation of scondary pole affcted by proposed construction | |
| BAGUIO CITY: Parts of Honeymoon - Holy Ghost (parts of Purok 6 and areas along Honeymoon Road, from Megatower Residences towards Maymay Store, including Barangay Hall) | Relocation of primary pole affected by ongoing construction | |
| LA TRINIDAD: Parts of Balili (parts of Pinespark, Tebteb) and parts of Inselbeg, Lubas | Installation of distribution transformer and rerouting of lines due to load splitting | |
| February 14, 2026 Saturday 9:00 AM to 5:00 PM | BOKOD: Sitio Namood and Pilpiloy, Pito | |
| BAGUIO CITY: Parts of Irisan (Apugan, Purok 12, parts of Purok 10, parts of Cypress Village, Cypress Christian Foundation School and Tengdow Road) | Relocation of primary pole and extension of primary lines | |
| LA TRINIDAD: Parts of Alapang (Alapang Proper and Areas near Barangay Hall, Etong, Bagto) and whole of Alno; | Reconfiguration of lines for primary extension | |
| TUBLAY: Asin, Tuel, parts of Basil (Pangablan) | ||
| SABLAN: Whole of Balluay |
In BENECO’s advisory, all concerned Cable & Communication Companies are advised to inspect and institute necessary safety measures or actions on their cables or lines attached to the affected BENECO poles.
For more information and concerns, contact BENECO at any of these numbers:
Looking for more news and updates? Feel free to explore our BCG website and our official Facebook page. You may also check out our official BCG YouTube channel to catch a variety of video content.
SOURCE: BENECO