NGCP Power Interruption April 2, 2022

Date and TimeAreas AffectedPurpose
April 2, 2022
Saturday
6:00AM to 5:00 PM
Whole of SablanNGCP POWER
INTERRUPTION
- To facilitate
implementation of the following
activities:
1. Installation of
Load Break
switch at North
Sanitary Camp
at Str No.
(5LI1LTR-SAB)
BEC-SAB019tp
2. Correction of
Line Defects
along La
Trinidad-Sablan 69kV line
3. Uplifting of
Conductors at BENECO
Irisan tapping
point Str No.
(5LI1LTR-SAB)
BEC-SAB049tp
as per request
by BENECO.
4.Tapping/
Energization
of new current
and potential
transformers at
Hedcor 69kV
metering
facility-
Calot tapping
point.
5. Correction of
identified
defects at La
Trinidad
Substation

Note:
Restoration/
Normalization
time is
from 1600H
(04:00 PM)
to 1700H
(05:00PM)
Whole of La Trinidad
EXCEPT
Beckel (Lamut Area),
Parts of Ambiong LT
and Shilan
(near boundary
of Lamut)
WHOLE OF Baguio
City EXCEPT:

- Parts of Pacdal
(Liteng,
Maria Basa, Tiptop),
- Mines View Park,
- Gibraltar,
- Pucsusan,
- Lualhati Village,
- Outlook Drive,
- Lucnab,
- South Drive,
- Parts of Cabinet
Hill-Teachers Camp
Barangay
(Near and Along
South Drive Road),
- Country Club Village,
- Happy Hallow,
- DPS Compound,
- Green Water
Village,
- Military Cut-off,
- Sta. Scholastica
Village,
- Scout Barrio,
- Upper Dagsian,
- Lower Dagsian,
- Hillside,
- Gabriela Silang,
- Camp 7,
- Camp 8,
- Poliwes,
- San Vicente,
- Parts of Bakakeng
Norte/Sur
(Ciudad Grande,
Eagle Crest,
Montebello Village),
- Loakan-Apugan,
- Loakan Proper,
- Loakan Liwanag,
- Atok Trail,
- Kias,
- Fort Del Pilar,
- PMA
Whole of TUBA
EXCEPT:

- Camp 4,
- Camp 3,
- Twin Peaks,
- Tabaan Sur,
- Camp 1
Parts of Tublay,
Tuel, Acop until
WINACA



BENECO Power Interruption March 29- April 1, 2022

Date and TimeAreas AffectedPurpose
March 29, 2022
Tuesday
9:00 AM to 5:00 PM
BAGUIO CITY:
Parts of Richgate
Square Phase III-
Camp 7
Relocation of
Secondary Pole
affected by
proposed driveway
BAGUIO CITY:
Parts of:
Eagle Crest
Phase III,
Bakakeng Norte/Sur
Reconfiguration of
Lines affected by
proposed house
construction
March 30, 2022
Wednesday
7:00AM to 5:00 PM
BUGUIAS:
Parts of:
- Buyacaoan
- Lengaoan
- Amgaleyguey

BAKUN:
Parts of Gambang
Uprating of insulators
March 30, 2022
Wednesday
9:00AM to 5:00 PM
ITOGON:
Parts of:
- Makaag
- Aleb
- Baayan
- Gold Creek
- Ucab
Facilitate Line
Clearing
ITOGON:
Parts of Malasin, Ucab
Replacement of
Rotten Pole
BOKOD:
Parts of Hilltop,
Ambuklao
Facilitate Line
Clearing
ITOGON:
Parts of Ayosip and
Gusaran, Dalupirip
Reconfiguration of
Lines to improve
line clearance
March 30, 2022
Wednesday
10:00AM to 12:00 NN
BOKOD:
Parts of Ambuklao:
- Ambayec
- Bangao
- Tojakap
- Jangjang
- Inidian

Bobok-Bisal Proper
Pito Proper
Poblacion
(Cobabeng)
Energization of
Primary Lines under
the Sitio
Electrification
Program (SEP)
March 31, 2022
Thursday
9:00AM to 5:00 PM
TUBLAY:
Parts of Conocon,
Pomey-as and
Bangho, Daclan
Replacement of
Rotten Poles
TUBLAY:
Parts of Basil,
Bodehew,
Malanac,
Belong, Daclan
Relocation of Pole
affected by ongoing
lot excavation
April 1, 2022
Friday
9:00AM to 5:00 PM
MANKAYAN:
Parts of Duggong,
Taneg
Installation of
Private Transformer

Extension of
Primary Lines

Luzon Hydro Power Interruption March 29-30, 2022

Date and TimeAreas AffectedPurpose
March 29, 2022
Tuesday
8:00 AM to 5:00 PM
BAKUN:
Kayapa,
Parts of Sinacbat
(Lam-ew)

KIBUNGAN:
Tacadang

ILOCOS SUR:
Dipey, Apang, Alilem
Restoration of Line
Protection

Annual Testing,
Cleaning and
Repainting of
Substation Structure
March 30, 2022
Wednesday
8:00 AM to 5:00 PM



Cable & Communication Companies

In BENECO’s advisory, all concerned Cable & Communication Companies are advised to inspect and institute necessary safety measures or actions on their cables or lines attached to the affected BENECO poles.




For other questions and concerns:

For more information and concerns, contact BENECO at any of these numbers:

  • LANDLINE: 637-4400 local 605 to 607
  • SMART: 09088657202
  • GLOBE: 09175921698

For More News and Updates

Looking for more news and updates? Feel free to explore our BCG website and our official Facebook page. You may also check out our official BCG YouTube channel to catch a variety of video content.

SOURCE: BENECO



How do you feel about this?

Happy
1
Sad
0
Shocked
0
Not Sure
0

You may also like

Comments are closed.