BENECO Power Interruption Schedule from June 19-24, 2023





As announced by the Benguet Electric Cooperative (BENECO), here are areas in Baguio City and Benguet that will be affected by scheduled power interruptions by BENECO and NGCP from Monday, June 19, 2023, to Saturday, June 24, 2023.





Tap to Read More

BENECO Power Interruption (June 19-24, 2023)

Areas AffectedPurpose
June 19, 2023
Monday
9:00 AM to 5:00 PM
BAGUIO CITY:
Parts of Maxicar Village,
Purok Sadjo,
Loakan Proper
Replacement of
secondary jumpers
and correction
secondary bushing
June 20, 2023
Tuesday
9:00 AM to 5:00 PM
BAGUIO CITY:
Along Legarda Rd.
(Nevada's Residence)
Tapping and
energization of
private transformers
BAGUIO CITY:
Green Summerville
Subd., Bakakeng
Norte/Sur
Reconfiguration of
assemblies
to improve line
clearance
June 21, 2023
Wednesday
9:00 AM to 9:15 AM

4:45 PM to 5:00 PM
LA TRINIDAD:
Parts of Ambiong LT
(near Lamut) and
whole of Beckel

BAGUIO CITY:
Parts of Pacdal
(Liteng, Maria Basa,
Tiptop),
Mines View Park,
Gibraltar, Pucsusan,
Lualhati Village,
Outlook Drive, Lucnab

ITOGON:
Tuding, Ucab,
Gumatdang,
Loacan, parts of
Poblacion IT (Maligaya),
parts of Tinongdan
(Boneco, Guisset)

BOKOD:
Part of Ambuklao
(Sombrero,
Hilltop)
Facilitate opening
and closing of
Pacdal Circle DS
June 21, 2023
Wednesday
9:15 AM to 4:45 PM
BAGUIO CITY:
Parts of Pacdal
(Liteng, Maria Basa),
Mines View Park,
parts of Gibraltar,
Pucsusan,
Lualhati Village,
Outlook Drive,
Lucnab

ITOGON:
Tuding,
Ucab,
Gumatdang,
parts of Loacan
parts of Poblacion IT
(Maligaya)
Reconfiguration of
primary assemblies
for primary extension

Energization of
sole-use transformer

Relocation of
primary pole affected
by
ongoing building
construction

Facilitate ROW
cleaning
June 21, 2023
Wednesday
9:00 AM to 5:00 PM
LA TRINIDAD:
Balucas and Conit,
Shilan
Relocation of
primary pole with
eroded base
LA TRINIDAD:
Parts of Alapang
Barangay
(parts of Camp Bado
Dangwa)
Uprating of communal
distribution transformer
from 50kVA to 167kVA
June 22, 2023
Thursday
9:00 AM to 5:00 PM
BAGUIO CITY:
Parts of Ponce St. and
2nd Rd.,
Quezon Hill Proper
Uprating of communal
distribution transformer
from 50kVA to 167kVA
BAGUIO CITY:
Parts of Upper and
Lower Kitma,
Bakakeng Central
Reconfiguration of
assemblies for
primary line extension
June 23, 2023
Friday
9:00 AM to 5:00 PM
BAGUIO CITY:
Parts of Irisan
(Catalino Drive,
Genesis Rd., Purok 5)

TUBA:
Genesis Point
Village, Tadiangan
Tapping and energization
of private transformers
BAGUIO CITY:
Parts of Lourdes Subd.
(Morning Star St.,
Mystical Rd.,
parts of Queen of
Apostle St. tapped
at Mystical Rd.
Relocation of
primary pole
affected by ongoing
construction
June 24, 2023
Saturday
9:00 AM to 5:00 PM
BAGUIO CITY:
Parts of SLU-SVP
Old Site and Purok 9,
Bakakeng Norte/Sur
Relocation of
secondary pole
affected by
road development
BAGUIO CITY:
Parts of Camp 7
(from Monticello Rd.,
Richgate Square
Phase 1 2 3,
Lexber Heights,
Mangitit)

Parts of Bakakeng
Norte/Sur
(Tetep-an Village,
Crestwood Court,
Montebello Subd.,
Bareng Drive,
SLU Bakakeng Campus,
Eagle Crest
Phase 1 & 2,
Ciudad Grande
Phase 1 & 2,
Goshen Land,
Forest Gold,
up to Bakakeng
New Site)
Relocation of
primary pole
affected by ongoing
construction

Facilitate ROW
clearing




Cable & Communication Companies

In BENECO’s advisory, all concerned Cable & Communication Companies are advised to inspect and institute necessary safety measures or actions on their cables or lines attached to the affected BENECO poles.




For other questions and concerns:

For more information and concerns, contact BENECO at any of these numbers:

  • LANDLINE: 637-4400 local 605 to 607
  • SMART: 09088657202
  • GLOBE: 09175921698

For More News and Updates

Looking for more news and updates? Feel free to explore our BCG website and our official Facebook page. You may also check out our official BCG YouTube channel to catch a variety of video content.

SOURCE: BENECO



Ads