The Benguet Electric Cooperative, Inc., (BENECO) has released the schedule of Electric Service Interruption for August 3 to 8, 2020 affecting several areas in Baguio City and Benguet
Here are the following areas in Baguio City and Benguet affected by the scheduled power interruption scheduled on August 3 to August 8, 2020.
Date | Areas Affected | Purpose |
Monday August 3 2020 9:00 AM to 5:00 PM | Baguio City: Parts of Amsing Pacdal | Rehabilitation of secondary line |
Baguio City: Parts of West Montecillo, Camp 7 | Relocation of 1 unit 30 footer steel pole | |
Baguio City: Parts of Lower Magsaysay | Installation of additional 75 kVA communal transformer to improve power quality | |
Tuesday August 4 2020 9:00 AM to 5:00 PM | Baguio City: Parts of Dontogan | Uprating of communal transformer from 15 kVA to 37.5 kVA |
Baguio City: Parts of Dontogan (Purok 10 and nearby areas) | Relocation of 30 footer secondary pole | |
Tuba: Parts of Taloy Sur to Tabaan Norte | Installation of intermediate primary pole at Parasipis, Tabaan Norte | |
Baguio City: Teacher’s Village, Sto. Tomas Proper | Relocation and reconfiguration of primary pole assembly; replacement of rotten crossarms | |
La Trinidad: Payew, Alno | Relocation of 1 unit 30 feet steel pole | |
Wednesday August 5 2020 9:00 AM to 5:00 PM | Baguio CIty: Montebello, Bakakeng | Replacement of rotten crossarms |
Itogon: Parts of Skyview, Virac | Replacement of GI pole with 30 feet steel pole | |
Bakun: Dalingaoan, Sinacbat, Bakun | Uprating of 13.2 kV insulatiors to 23 kV | |
Bakun: Lipunan, Sinacbat, Bakun | Uprating of 13.2 kV insulatiors to 23 kV | |
Baguio City: San Luis Extension | Replacement of rotten secondary pole and retirement of guy wire |
Date | Areas Affected | Purpose |
Thursday August 6 2020 9:00 AM to 5:00 PM | Baguio City: Parts of Balsigan | Replacement of Rotten Pole at Purok 5, Balsigan |
Bakun: Parts of Sinacbat, Bakun | Uprating of 13.2 kV insulatiors to 23 kV | |
Bakun: Tinmapog, Dalipey, Bakun | Uprating of 13.2 kV insulatiors to 23 kV | |
Baguio City: Parts of Km 3, Asin Road | Extension of secondary line | |
Baguio City: Parts of City Camp Proper | Correction of Leaning Bayonet | |
Baguio City: Parts of Brookspoint, Aurora Hill | Correction of Leaning Bayonet | |
Friday August 7 2020 9:00 AM to 5:00 PM | Atok: Parts od Cattubo, Atok (near Berang) | Replacement of Rotten Pole at Purok 5, Balsigan |
Baguio City: Parts of KM 6, Purok 2, Green Valley, Dontogan | Massive Clearing | |
Baguio City: Whole of Lucnab | Relocation of Pole at Purok 4A/4B affected by DPWH project | |
Saturday August 8 2020 9:00 AM to 5:00 PM | Baguio City: Whole of Trancoville, Parts of Malvar, Whole of Happy Homes, Old Lucban | Retirement of Poles along Trancoville Diversion of load from Feeder 7 to Feeder 5A |
Baguio City: Parts of Camp 8, Baguio City | Rerouting of Secondary Line |
In BENECO’s advisory, all concerned Cable & Communication Companies are advised to inspect and institute necessary safety measures or actions on their cables or lines attached to the affected BENECO poles.
Also, all consumers are advised to always consider all lines energized because power may be restored earlier than the scheduled time.
For more information and concerns, contact BENECO at any of these numbers:
Source: BENECO